The last 50 kilometres of NordBalt cable will be soon laid to the seabed

During the month long work in 2015 the special vessel Topaz Installer laid more than 50 kilometers of HVDC cable NordBalt in the Baltic Sea. Ship is completing the laying of the second same length section at the moment.

Most of the cable, almost 350 km of the 400 under-water cable, has been laid onto the seabed now.

The commissioning of the Lithuanian-Swedish interconnector is scheduled in December 2015.